Product Quantum (Rs. Cr) Long Term Rating Short Term Rating
Bank Loan Ratings 5500.00 ACUITE A- | Stable | Reaffirmed -
Total Outstanding Quantum (Rs. Cr) 5500.00 - -
 
Rating Rationale
­Acuité has reaffirmed a long-term rating of ‘ACUITE A-’ (read as ACUITE A minus) to the Rs. 5500 Cr. bank facilities of Versova Bandra Sea Link Limited (VBSLL). The outlook is ‘Stable’.

Rationale for Rating Reaffirmation
The rating reaffirmation considers the strategic importance of the project which will connect Versova to the Bandra-Worli Sea Link and further to the Mumbai-Coastal road. The rating further takes into account the extensive experience of Maharashtra State Road Development Corporation (MSRDC) in undertaking large strategic road projects in the state of Maharashtra. Further, the rating also draws comfort from the financial closure happened during the year along with equity infusion to the tune of ~Rs. 2600 Cr. received by VBSLL during FY2023(Prov.) and funding support until the project completion available to VBSLL from the Government of Maharashtra (GOM) under the tri-partite concession agreement signed by GOM, VBSLL and MSRDC. However the rating remains constrained by the substantial execution and demand risk the project is exposed to. It is at a very nascent stage and completion of the project without further time and cost overruns will continue to remain a key credit sensitivity.

About the Company
VBSLL, incorporated in April 2018 has been established to conceptualize, plan, design and construct Versova Bandra Sea Link, a project by Maharashtra State Road Development Corporation (MSRDC). Government of Maharashtra (GoM) has appointed MSRDC as the nodal agency for the development of a new sea link that will connect Bandra and Versova in Mumbai, Maharashtra on a Design, Build, Finance, and Operate and Transfer (DBFOT) basis. The project is intended to connect the Bandra end of the existing Bandra Worli Sea Link (BWSL) and to extend towards Versova as a new sea link. The main carriageway of the project will be located on the Arabian Sea, approximately 900m from the coast. The project would have a length of ~17.17 Km and shall connect the Bandra end of Bandra Worli Sea Link to Versova, near the Nana Nani Park. The project construction will entail the construction of the Main Sea Bridge of the project having a length of 9.6 Km, four Connectors at Bandra (1.17 Km), Otters Club (1.80 Km), Juhu Koliwada (2.80 Km) and Nana Nani Park (1.80 Km). The total estimated cost of the project was Rs. 9,943 crore which has now been revised upward to Rs. 11232.86 Cr. Out of the total, estimated project cost Rs. 5,500 crore will be funded by debt and the rest by equity.
 
Standalone (Unsupported) Rating
­Acuite BB / Stable
 
Analytical Approach
­Acuité has considered the standalone approach while assessing the business and financial risk profile of VBSLL and has factored in financial, operational and managerial support it receives from GoM through MSRDC by virtue of being a step-down subsidiary of the GoM. The rating factors in the 100 percent holding of MSRDC (a GoM entity) in VBSLL along with the strategically important role played by the entity in implementing a key infrastructure project in the state capital.
 

Key Rating Drivers

Strengths
Established track record of parent in the road infrastructure industry.
VBSLL is a subsidiary of MSRDC (100 per cent stake) and a step-down subsidiary of GoM. MSRDC, a corporation established and fully owned by the GoM, is a limited company incorporated in 1996. It is established to oversee large road infrastructure projects across the state of Maharashtra. MSRDC has successfully completed key projects such as Mumbai Pune Express Way (MPE), Bandra Worli Sea Link (BWSL) and Satara Kagal Road amognst others. MSRDC has also been tasked with the execution of the critical Hindu Hridaysamrat Balasaheb Thakare Maharashtra Samruddhi Mahamarg Project, a ~701 km project passing through 10 districts of Maharashtra which is also supported by GoM. It reported an operating profit of Rs. 1359 Cr. on an operating income of Rs. 1623 Cr. in FY2022 (Provisional). The Board of VBSLL comprises of civil servants appointed by the GoM. CEO of VBSLL also holds the post of Managing Director for MSRDC. VBSLL is tasked by MSRDC with the execution of the Versova Bandra Sea Link project in Mumbai. The project is designed to connect Versova, a neighbourhood in the suburb of Andheri to the Bandra -Worli Sea Link and further to the Mumbai Coastal Road with a view to reduce traffic congestion in the heart of the state capital. The strategically important nature to MSRDC and support from GoM ease the funding available to the project from various financial institutions.
Acuité believes the continued management of the company by MSRDC and support from GoM will be beneficial for VBSLL in the long term.

Equity infusion along with financial closure during FY2023 expected to accelerate the construction.
The current project cost is envisaged at around Rs. 11,233 Cr. out of which around Rs.999 Cr. has been incurred towards construction of the project and around 9% of physical progress has been achieved as on May 31, 2023. As on March 31, 2023, MSRDC has infused equity to the tune of ~Rs. 2300 Cr against Rs. 265 Cr. as on March 31, 2022. Further, the debt tie-ups have also been accomplished with SBI & UBI and the lenders in consortium have sanctioned a debt of Rs. 5500 Cr. towards construction of the project. Additionally, the company has free cash and bank balances available to the tune of ~Rs. 1400 Cr. as on March 31, 2023. Acuité believes that going forward the pace of construction is likely to pick up owing to funding being available in the form of surplus cash balances, equity infusion and debt tie-ups being completed.

Funding shortfall support agreement from Government of Maharashtra under the Concession Agreement.
A tripartite Concession Agreement has been executed in 2018 amongst VBSLL as the Concessionaire, MSRDC as the Sponsor & GoM as the Concessioning Authority. This agreement forms the basis of the support from GoM available to VBSLL. As per articles of the agreement in case of cash shortfall during the Operation Period and/or the Construction period or in case of cost overruns beyond the envisaged total project cost it would be met by the Concessioning Authority. The agreement also protects the Concessionaire by restricting the GoM from the construction of any competing roads and also provides for compensation to the Concessionaire if any such a road is constructed before the achievement of targeted traffic.
Weaknesses

Project execution risk and offtake risk
VBSLL is constructing the Versova Bandra Sea Link at an estimated cost of Rs. 11233 Cr. to be funded through equity of Rs. 5733 Cr. and term loan of Rs. 5500 Cr. This has been revised upward from Rs. 10917 Cr. earlier. The escalation is primarily on account of extension in expected commencement of operations from November 2025 to January 2027 and currently March 2028 on account of historical delays in construction caused by lockdowns brought on by COVID 19. The civil work and construction had commenced in April 2020 but the pace of work had been significantly affected by the lockdowns brought on by the second Covid 19 wave in early 2021. Further, the JV between Reliance Infrastructure and Astaldi initially was selected as the EPC contractor based on competitive bidding process. However, Reliance Infrastructure exited the JV and has transferred its stake to Apco Infratech in January 2022 with approval of MSRDC. This also caused a delay in financial closure. Further, the project is exposed to substantial execution risk as only 9% of the physical progress has been accomplished till date. The complex construction work has to be undertaken and consensus amongst various stakeholders will be required for getting final clearances required for the project completion. The project also remains susceptible to risk of litigations as was observed in the completion of Bandra Worli Sea Link (BWSL). This risk mitigated on account of support from MSRDC and funding shortfall support from GOM in the construction as well as operational period. From an offtake standpoint, VBSLL will be exposed to offtake risk in the initial stages as the connecting roads get constructed. Once the connecting roads are completed offtake risk will be reduced as the project aims to release traffic congestion in a very busy route (Western suburbs to Island City) in the Mumbai. The revenue pick up of the project is expected to be gradual. Since the operating cash flows will stabilise over a period of time, the repayment is expected to start in FY2030 in order to align operational cash flows to the debt service commitments.

Linkages to fiscal position of State of Maharashtra
Maharashtra is India’s leading industrial state, its gross state domestic product (GSDP) is expected (at current prices) to be Rs. 38.79 Lakh Cr. for FY2023-24 as against Rs 35.27 Lakh Cr. for FY2022-23 (RE). The fiscal deficit of Maharashtra for FY2022- 23 (RE) is increased to 2.70 percent of GSDP against 2.24 percent in FY2021-22. This increase is attributable to shortfall in revenue receipts. Any further adverse changes in the fiscal indicators of GoM factors the prolonged slowdown in industrial activities or socio-economic challenges faced by Maharashtra, can significantly impact MSRDC and VBSLL, and will be a key monitoring factor.

ESG factors Relevant for rating
­Not applicable 
 
Rating Sensitivities
  • ­Timely completion of project and commencement of commercial operations without significant cost overruns.
 
Liquidity Position
Adequate
VBSSL has an adequate liquidity position. Acuité does not foresee any positive net cash accruals in the first year of operations. However, as on March 31, 2023(prov.) the company has cash and bank balances of around ~Rs. 1400 Cr. Further, VBSSL will continue to get funding support from GoM through the concession agreement for the construction as well as operational period. The maturing debt repayment is expected to commence from FY2030. The liquidity of the company is likely to remain adequate over the medium term on account of ability of GoM and promoters i.e. MSRDC to fund the liquidity deficit in the initial stage of operations.
 
Outlook: Stable
Acuité believes that VBSLL will maintain a 'Stable' credit profile over the medium term on the back of support from GoM. The outlook may be revised to 'Positive' if the company is able to achieve substantial progress in terms of physical construction of the project as scheduled and exhibits ability to generate cash flows commensurate as per its debt. Conversely, the outlook may be revised to 'Negative' in case of delay in commencement of commercial operations and slower than expected pick up in revenues affecting its debt servicing ability.
 

Particulars Unit FY 23 (Provisional) FY 22 (Actual)
Operating Income Rs. Cr. 0.00 0.00
PAT Rs. Cr. (0.02) (0.02)
PAT Margin (%) 0.00 0.00
Total Debt/Tangible Net Worth Times 0.15 1.24
PBDIT/Interest Times 15.10 7.67
Status of non-cooperation with previous CRA (if applicable)
­Not Applicable
 
Any other information
­Not Applicable
 
Applicable Criteria
• Infrastructure Sector: https://www.acuite.in/view-rating-criteria-51.htm
• Default Recognition: https://www.acuite.in/view-rating-criteria-52.htm
• Application Of Financial Ratios And Adjustments: https://www.acuite.in/view-rating-criteria-53.htm
• Group And Parent Support: https://www.acuite.in/view-rating-criteria-47.htm

Note on complexity levels of the rated instrument
­In order to inform the investors about complexity of instruments, Acuité has categorized such instruments in three levels: Simple, Complex and Highly Complex. Acuite’ s categorisation of the instruments across the three categories is based on factors like variability of the returns to the investors, uncertainty in cash flow patterns, number of counterparties and general understanding of the instrument by the market. It has to be understood that complexity is different from credit risk and even an instrument categorized as 'Simple' can carry high levels of risk. For more details, please refer Rating Criteria “Complexity Level Of Financial Instruments” on www.acuite.in.
 

Date Name of Instruments/Facilities Term Amount (Rs. Cr) Rating/Outlook
28 Mar 2022 Proposed Term Loan Long Term 5000.00 ACUITE A- | Stable (Reaffirmed)
Proposed Term Loan Long Term 500.00 ACUITE A- | Stable (Reaffirmed)
24 Nov 2021 Proposed Term Loan Long Term 5000.00 ACUITE A- | Stable (Reaffirmed)
21 Aug 2020 Proposed Term Loan Long Term 5000.00 ACUITE A- | Stable (Assigned)
­

Lender’s Name ISIN Facilities Date Of Issuance Coupon Rate Maturity Date Quantum (Rs. Cr.) Complexity Level Rating
State Bank of India Not Applicable Term Loan Not available Not available Not available 3000.00 Simple ACUITE A- | Stable | Reaffirmed
Union Bank of India Not Applicable Term Loan Not available Not available Not available 2500.00 Simple ACUITE A- | Stable | Reaffirmed
­

Contacts
Analytical Rating Desk
About Acuité Ratings & Research

Acuité Ratings & Research Limitedwww.acuite.in