|
Product | Quantum (Rs. Cr) | Long Term Rating | Short Term Rating |
Bank Loan Ratings | 5500.00 | ACUITE A- | Stable | Reaffirmed | - |
Total Outstanding Quantum (Rs. Cr) | 5500.00 | - | - |
Rating Rationale |
Acuité has reaffirmed a long-term rating of ‘ACUITE A-’ (read as ACUITE A minus) to the Rs. 5500 Cr. bank facilities of Versova Bandra Sea Link Limited (VBSLL). The outlook is ‘Stable’.
Rationale for Rating Reaffirmation The rating reaffirmation considers the strategic importance of the project which will connect Versova to the Bandra-Worli Sea Link and further to the Mumbai-Coastal road. The rating further takes into account the extensive experience of Maharashtra State Road Development Corporation (MSRDC) in undertaking large strategic road projects in the state of Maharashtra. Further, the rating also draws comfort from the financial closure happened during the year along with equity infusion to the tune of ~Rs. 2600 Cr. received by VBSLL during FY2023(Prov.) and funding support until the project completion available to VBSLL from the Government of Maharashtra (GOM) under the tri-partite concession agreement signed by GOM, VBSLL and MSRDC. However the rating remains constrained by the substantial execution and demand risk the project is exposed to. It is at a very nascent stage and completion of the project without further time and cost overruns will continue to remain a key credit sensitivity.
|
About the Company |
VBSLL, incorporated in April 2018 has been established to conceptualize, plan, design and construct Versova Bandra Sea Link, a project by Maharashtra State Road Development Corporation (MSRDC). Government of Maharashtra (GoM) has appointed MSRDC as the nodal agency for the development of a new sea link that will connect Bandra and Versova in Mumbai, Maharashtra on a Design, Build, Finance, and Operate and Transfer (DBFOT) basis. The project is intended to connect the Bandra end of the existing Bandra Worli Sea Link (BWSL) and to extend towards Versova as a new sea link. The main carriageway of the project will be located on the Arabian Sea, approximately 900m from the coast. The project would have a length of ~17.17 Km and shall connect the Bandra end of Bandra Worli Sea Link to Versova, near the Nana Nani Park. The project construction will entail the construction of the Main Sea Bridge of the project having a length of 9.6 Km, four Connectors at Bandra (1.17 Km), Otters Club (1.80 Km), Juhu Koliwada (2.80 Km) and Nana Nani Park (1.80 Km). The total estimated cost of the project was Rs. 9,943 crore which has now been revised upward to Rs. 11232.86 Cr. Out of the total, estimated project cost Rs. 5,500 crore will be funded by debt and the rest by equity.
|
Standalone (Unsupported) Rating |
Acuite BB / Stable |
Analytical Approach |
Acuité has considered the standalone approach while assessing the business and financial risk profile of VBSLL and has factored in financial, operational and managerial support it receives from GoM through MSRDC by virtue of being a step-down subsidiary of the GoM. The rating factors in the 100 percent holding of MSRDC (a GoM entity) in VBSLL along with the strategically important role played by the entity in implementing a key infrastructure project in the state capital.
|
Key Rating Drivers
Strengths |
Established track record of parent in the road infrastructure industry.
VBSLL is a subsidiary of MSRDC (100 per cent stake) and a step-down subsidiary of GoM. MSRDC, a corporation established and fully owned by the GoM, is a limited company incorporated in 1996. It is established to oversee large road infrastructure projects across the state of Maharashtra. MSRDC has successfully completed key projects such as Mumbai Pune Express Way (MPE), Bandra Worli Sea Link (BWSL) and Satara Kagal Road amognst others. MSRDC has also been tasked with the execution of the critical Hindu Hridaysamrat Balasaheb Thakare Maharashtra Samruddhi Mahamarg Project, a ~701 km project passing through 10 districts of Maharashtra which is also supported by GoM. It reported an operating profit of Rs. 1359 Cr. on an operating income of Rs. 1623 Cr. in FY2022 (Provisional). The Board of VBSLL comprises of civil servants appointed by the GoM. CEO of VBSLL also holds the post of Managing Director for MSRDC. VBSLL is tasked by MSRDC with the execution of the Versova Bandra Sea Link project in Mumbai. The project is designed to connect Versova, a neighbourhood in the suburb of Andheri to the Bandra -Worli Sea Link and further to the Mumbai Coastal Road with a view to reduce traffic congestion in the heart of the state capital. The strategically important nature to MSRDC and support from GoM ease the funding available to the project from various financial institutions. Acuité believes the continued management of the company by MSRDC and support from GoM will be beneficial for VBSLL in the long term. Equity infusion along with financial closure during FY2023 expected to accelerate the construction. The current project cost is envisaged at around Rs. 11,233 Cr. out of which around Rs.999 Cr. has been incurred towards construction of the project and around 9% of physical progress has been achieved as on May 31, 2023. As on March 31, 2023, MSRDC has infused equity to the tune of ~Rs. 2300 Cr against Rs. 265 Cr. as on March 31, 2022. Further, the debt tie-ups have also been accomplished with SBI & UBI and the lenders in consortium have sanctioned a debt of Rs. 5500 Cr. towards construction of the project. Additionally, the company has free cash and bank balances available to the tune of ~Rs. 1400 Cr. as on March 31, 2023. Acuité believes that going forward the pace of construction is likely to pick up owing to funding being available in the form of surplus cash balances, equity infusion and debt tie-ups being completed. Funding shortfall support agreement from Government of Maharashtra under the Concession Agreement. A tripartite Concession Agreement has been executed in 2018 amongst VBSLL as the Concessionaire, MSRDC as the Sponsor & GoM as the Concessioning Authority. This agreement forms the basis of the support from GoM available to VBSLL. As per articles of the agreement in case of cash shortfall during the Operation Period and/or the Construction period or in case of cost overruns beyond the envisaged total project cost it would be met by the Concessioning Authority. The agreement also protects the Concessionaire by restricting the GoM from the construction of any competing roads and also provides for compensation to the Concessionaire if any such a road is constructed before the achievement of targeted traffic. |
Weaknesses |
Project execution risk and offtake risk |
ESG factors Relevant for rating |
Not applicable |
Rating Sensitivities |
|
Liquidity Position |
Adequate |
VBSSL has an adequate liquidity position. Acuité does not foresee any positive net cash accruals in the first year of operations. However, as on March 31, 2023(prov.) the company has cash and bank balances of around ~Rs. 1400 Cr. Further, VBSSL will continue to get funding support from GoM through the concession agreement for the construction as well as operational period. The maturing debt repayment is expected to commence from FY2030. The liquidity of the company is likely to remain adequate over the medium term on account of ability of GoM and promoters i.e. MSRDC to fund the liquidity deficit in the initial stage of operations.
|
Outlook: Stable |
Acuité believes that VBSLL will maintain a 'Stable' credit profile over the medium term on the back of support from GoM. The outlook may be revised to 'Positive' if the company is able to achieve substantial progress in terms of physical construction of the project as scheduled and exhibits ability to generate cash flows commensurate as per its debt. Conversely, the outlook may be revised to 'Negative' in case of delay in commencement of commercial operations and slower than expected pick up in revenues affecting its debt servicing ability.
|
Particulars | Unit | FY 23 (Provisional) | FY 22 (Actual) |
Operating Income | Rs. Cr. | 0.00 | 0.00 |
PAT | Rs. Cr. | (0.02) | (0.02) |
PAT Margin | (%) | 0.00 | 0.00 |
Total Debt/Tangible Net Worth | Times | 0.15 | 1.24 |
PBDIT/Interest | Times | 15.10 | 7.67 |
Status of non-cooperation with previous CRA (if applicable) |
Not Applicable |
Any other information |
Not Applicable |
Applicable Criteria |
• Infrastructure Sector: https://www.acuite.in/view-rating-criteria-51.htm • Default Recognition: https://www.acuite.in/view-rating-criteria-52.htm • Application Of Financial Ratios And Adjustments: https://www.acuite.in/view-rating-criteria-53.htm • Group And Parent Support: https://www.acuite.in/view-rating-criteria-47.htm |
Note on complexity levels of the rated instrument |
In order to inform the investors about complexity of instruments, Acuité has categorized such instruments in three levels: Simple, Complex and Highly Complex. Acuite’ s categorisation of the instruments across the three categories is based on factors like variability of the returns to the investors, uncertainty in cash flow patterns, number of counterparties and general understanding of the instrument by the market. It has to be understood that complexity is different from credit risk and even an instrument categorized as 'Simple' can carry high levels of risk. For more details, please refer Rating Criteria “Complexity Level Of Financial Instruments” on www.acuite.in.
|
|
|
|
|||||||||||||||||||||||||||
|
|
Contacts |
Analytical | Rating Desk |
About Acuité Ratings & Research |
Acuité Ratings & Research Limited | www.acuite.in |