Product | Quantum (Rs. Cr) | Long Term Rating | Short Term Rating |
Bank Loan Ratings | 9000.00 | ACUITE A- | Stable | Reaffirmed | - |
Bank Loan Ratings | 800.00 | Not Applicable | Withdrawn | - |
Total Outstanding | 9000.00 | - | - |
Total Withdrawn | 800.00 | - | - |
Rating Rationale |
Acuité has reaffirmed its long-term rating of ‘ACUITE A-’ (read as ACUITE A minus) on the Rs. 9,000 crore bank facilities of MSRDC Pune Ring Road Limited (MPRRL). The outlook is ‘Stable’.
Acuite has withdrawn its long-term rating on Rs.800.00 Cr. proposed bank facilities without assigning any rating as it is a proposed facility of MSRDC Pune Ring Road Limited (MPRRL). The rating is being withdrawn on account of request received from the company. The rating withdrawal is in accordance with Acuité's policy on withdrawal of rating as applicable to the respective facility / instrument. Rationale for the rating The rating reaffirmation reflects established track record of operations of MPRRL’s parent, Maharashtra State Road Development Corporation (MSRDC) in the infrastructural construction segment, strong resource mobilization ability on account of continued operational and financial support from MSRDC and Government of Maharashtra (GoM). The rating factors in support for any shortfall in funding which the company will receive from GoM as per the signed Concession Agreement (CA). However, the rating is constrained by the nascent stage of the project with appointment date is yet to be finalized by the authority, pending equity infusion by the sponsor and the timely execution of engineering, procurement & construction (EPC) works. The rating also factors in any adverse changes in the fiscal indicators of GoM due to factors such as the prolonged slowdown in industrial activities or socio-economic challenges faced by Maharashtra. |
About the Company |
Incorporated in January 2022, MPRRL is a wholly owned subsidiary of MSRDC formed for implementation of access-controlled greenfield expressway having length of ~65.45 km around the city of Pune, starting from Urse toll plaza (near YCEW) and culminating at Shivare (near NH-48) on Design, Built, Finance, Operate & Transfer (DBFOT) basis in accordance with the Concession Agreement signed between Sponsor (MSRDC), Authority (GoM) and Borrower (MPRREL). The current directors of the company are Mr. Anilkumar Baliram Gaikwad, Mr. Sahebrao Kundlikrao Survase, Mr. Rajesh Bhagwan Patil and Mr. Manuj Jindal.
|
Unsupported Rating |
Acuite BB+ | Stable |
Analytical Approach |
Acuité has considered the standalone approach while assessing the business and financial risk profile of MPRRL and has factored in financial, operational and managerial support it receives from GoM through MSRDC by virtue of it being a step-down subsidiary of the GoM. The rating factors in the 100 percent shareholding of MSRDC in MPRRL along with the strategically important role played by the entity in implementing a key infrastructure project in the state.
|
Key Rating Drivers |
Strengths |
Extensive experience of the promoter in the infrastructure industry and support from GoM
MPRRL, which is the concessionaire, is a wholly owned subsidiary of MSRDC, which in turn is fully owned by the GoM. MSRDC, the sponsor of the project has been appointed as the implementation agency for the development of access-controlled greenfield expressway around the city of Pune. MSRDC has an extensive experience in the infrastructure industry and has successfully completed several key projects such as Mumbai Pune Express Way (MPEW), Bandra Worli Sea Link (BWSL), etc. The GoM exercises significant control over the working of MSRDC through its board of directors. All the directors are nominated by the GoM from time to time. The key management personnel and the board of directors of MPRRL comprise members drawn from the senior management of MSRDC. Acuite believes MPRRL’s linkages with the GoM through its sponsor MSRDC will provide adequate support to the credit profile of the company. Key location of the project with increased convenience to user leading to ease in toll collection A significant portion of the highway traffic plying between Mumbai to Bangalore is expected to use the planned ring road and will ease the intensity of traffic on the present NH-48 passing through the Pune city. As per the CA, the tenure of the concession period will be 40 years from the date of appointment of the concessionaire, which include 3.5 years of construction period for EPC contractor. The Scheduled Commercial Operation Date for the Project is 3.5 years days from date of appointment which is yet to be decided by the GoM. The company will be collecting toll income on the road from the date of achievement of COD. Funding shortfall support agreement from GoM under the Concession Agreement A tripartite CA is executed amongst the Borrower, as the Concessionaire, MSRDC as the Sponsor and GoM as the Concessioning Authority. This agreement forms the basis of the support from GoM which will be available to MPRRL. As per articles of the CA, any cash shortfall during the operation period and/or the construction period or in case of cost overruns beyond the envisaged total project cost would be met by the Concessioning Authority. The estimated project cost as per the CA is Rs.15,138.56 crores which will be funded by the means of debt funding which is already tied up, as well as equity contribution by the sponsor. The debt availed by the company will be serviced from the toll collection, which the company will be receiving after the achievement of COD. |
Weaknesses |
Nascent stage of project with significant implementation risk
The CA for the Pune Ring Road Project has been signed by the authority. Further, MSRDC is responsible for making timely land availability for the construction work. As on 7th February 2025, MSRDC has already acquired 96 percent of the total land. MSRDC proposes to issue the letter of award to appointed EPC contractors after the finalization of appointment date by the authority which is yet to be done. Given the greenfield nature of the project, the company is exposed to various risks including cost and time overruns. However, the project is split into 5 packages and awarded to multiple contractors, which mitigates the risk of failure of any individual contractor. The GoM as per the Article 25 of the CA would also provide equity shortfall support during the construction period that mitigates any funding risk and cost overruns. Linkages to the fiscal position of Maharashtra Maharashtra is India’s leading industrial state, its gross state domestic product (GSDP) is expected (at current prices) to be Rs. 42.67 Lakh Cr. for FY2024-25 as against Rs 38.79 Lakh Cr. for FY2023-24 (RE). The fiscal deficit of Maharashtra for FY2024-25 is targeted at 2.6 percent of GSDP against 2.8% percent in FY2023-24 (RE). Any adverse changes in the fiscal indicators of GoM due to factors such as the prolonged slowdown in industrial activities or socio-economic challenges faced by Maharashtra may have a significant impact on MPRRL and will be a key monitoring factor. |
Assessment of Adequacy of Credit Enhancement under various scenarios including stress scenarios (applicable for ratings factoring specified support considerations with or without the “CE” suffix) |
Support from GoM Stress case Scenario |
Rating Sensitivities |
|
Liquidity Position |
Adequate |
Acuité expects the cashflows from operations to remain negative for the first few years of operations for MPRRL. However, MPRRL will continue to get support from GoM under the CA during the construction as well as operational period. The debt repayment of the facility is expected to commence after 1.5 year from the achievement of COD as per the agreement. The liquidity of the company is likely to remain adequate over the medium term on account of continued support from GoM and MSRDC to fund the liquidity deficit in the initial stage of operations.
|
Outlook : Stable |
|
Other Factors affecting Rating |
None |
Key Financials : |
Not available, as the company was incorporated on 12-01-2022
|
Status of non-cooperation with previous CRA (if applicable) |
Not Applicable |
Interaction with Audit Committee anytime in the last 12 months (applicable for rated-listed / proposed to be listed debt securities being reviewed by Acuite) |
Not applicable |
Any other information |
None |
Applicable Criteria |
• Default Recognition :- https://www.acuite.in/view-rating-criteria-52.htm • Infrastructure Sector: https://www.acuite.in/view-rating-criteria-51.htm • Application Of Financial Ratios And Adjustments: https://www.acuite.in/view-rating-criteria-53.htm • Group And Parent Support: https://www.acuite.in/view-rating-criteria-47.htm • Public Finance - State Government Ratings: https://www.acuite.in/view-rating-criteria-26.htm • Explicit Credit Enhancements: https://www.acuite.in/view-rating-criteria-49.htm |
Note on complexity levels of the rated instrument |
|
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
*Annexure 2 - List of Entities (applicable for Consolidation or Parent / Group / Govt. Support) | ||||||
|
||||||
Contacts |
About Acuité Ratings & Research |
© Acuité Ratings & Research Limited. All Rights Reserved. | www.acuite.in |