Experienced management along with extensive experience of sponsor
Gangamai Kalyan ACR Private Limited (GKACR) is a JV between Gangamai Industries and Constructions Limited (51%) and Kalyan Toll Infrastructure Limited (49%). GKACR was established in December 2020. KTIL provides complete technical assistance to GKACR and has more than a decade of experience in the infrastructural construction business and has an established track record of successful project completion of more than Rs.1600.00 crore worth of projects. KTIL is promoted by Tikamchand Garg, Rajesh Kumar Garg, Amit Kumar Garg, and Jyoti Soni. GIACL is a part of Padmakar Mulay Group of Companies of Aurangabad, incorporated in May 1999. The group is led by Mr. Padmakar H Mulay an industrialist having more than 45 years of rich experience. GICL has provided the financial support to project undertaken by GKACR wherein ~Rs.189 crore has already been infused by GICL. Acuite believes that the company will benefit from the experienced track record of operations of the sponsor- GICL in the near to medium term.
Annuity-based revenue model
The project being constructed under hybrid annuity model. Under this model, NHAI reimburses 60% of the construction cost on milestone basis thereafter making bi-annual annuity payments over the concession period to the concessionaire post completion of the construction. As a result, the company does not bear any traffic risk as it recovers whole of the capital cost through annuity receipts. Further, bi-annual operational & maintenance expense along with interest cost reimbursement will be given to the concessionaire during the concession phase. The company has completed physical progress upto 87-88% and is expected to complete 100% construction by August 2023.
Waterfall Mechanism in ESCROW account and Debt-service reserve account (DSRA)
GKAPL has escrow mechanism through which cash flows from authority is routed and used for payment as per the defined payment waterfall. The company also has to maintain DSRA equivalent to 6 months interest and principal is to be maintained on or prior to COD till tenure of the Facility. Further, corporate guarantee of sponsor is available. Any shortfall in debt servicing and shortfall in resources required for completion of project are to be met through support from GICL.
|
Susceptibility of delay in completion of project
The project is under construction phase and is 87-88 percent complete as on date. Earlier the project was expected to be completed by March 2023. The project execution is delayed due to non-availability of encumbrance free land, delay in possession of land required for construction, monsoon season, etc. The company had applied for an approval of extension of time of 270 days in the last year, out of which 105 days extension was approved by the authority and the revised COD date stood at June 2023. The company has further requested for an approval for extension in the time by 210 days, which is yet to be approved by the authority. As the approval is yet to be received, the project is susceptible to execution risk leading to delay in the receipts of the annuity payments and increase in the operational and interest expenses. The project cost which earlier stood at ~Rs.952 crore is now revised at Rs.1138 crore adjusting the inflation. The SPV has received 4 out of the 5 milestone payments. The company expects to receive the last milestone payment by the end of July 2023. Acuite believes that timely completion of project will remain a key rating sensitivity.
Delay in receipt of annuity, due to delayed project completion
The project developed by GKACR is an annuity-based revenue model in which the NHAI, will make annuity payments over the concession period to the concessionaire. As per the concession agreement, the GKACR is expected to receive a semi-annual annuity over the concession period as per CA. As the project is delayed, the annuity payments which were earlier supposed to start from August 2023 will be delayed depending on the COD (annuity starts from 6 months from date of COD).
|