Product | Quantum (Rs. Cr) | Long Term Rating | Short Term Rating |
Bank Loan Ratings | 30.00 | ACUITE A- | Stable | Assigned | - |
Total Outstanding | 30.00 | - | - |
Total Withdrawn | 0.00 | - | - |
Rating Rationale |
Acuite has assigned its long-term rating of 'ACUITE A-' (read as ACUITE A minus) on the Rs.30.00 Cr. bank facilities of BNC Palsiddha Infra Private Limited (BNCPIPL). The outlook is 'Stable'.
Rationale for Rating The rating considers the completion of project along with all the milestone payments received from PWD (Government of Maharashtra) and 4 annuity payments has been received by the company. Further, the rating factors in the adequate liquidity of the company in the form of cash and cash equivalents and escrow mechanism. Acuite has also considered the technical support and funding support in the form of corporate guarantees for the loan availed from the sponsor while arriving at the rating. However, the rating is constrained by risk related to delay in annuity payments and changes in operational and interest cost. |
About the Company |
Pune – Based, BNC Palsiddha Infra Private Limited was incorporated in 2018. The company is engaged in civil construction works of roads and development projects. It also undertakes upgradation of Road joining to District place to Taluka place in Washim district border to Rithad with a length of 45.40 km in Maharashtra. Directors of the company are Mr. Rajesh Prakash Chaudhari, Mr. Arjun Bhivasan Kate and Mr. Girish Bhagwat Chaudhari.
|
Unsupported Rating |
Not Applicable |
Analytical Approach |
For arriving at the rating, Acuité has considered the standalone credit profile of BNCPIPL. Further, Acuité has also considered escrow mechanism, as specified in the loan sanction letter while arriving at the rating.
|
Key Rating Drivers |
Strengths |
Strong counterparty linked revenue profile
The company has entered into a concession agreement with PWD (Govt. of Maharashtra) for improvement in roads to Taluka place in Washim district border to Rithad in Maharashtra in September 2018. The project was completed in December 2023. The concession is granted to the company for 10 years after the CoD and during the concession bi-annual annuity payment would be paid by MPWD. The company has received the 4 annuity payments for the completed project by May 24. Along with annuity payments, interest shall be payable to BNCPIPL on reducing balance of completion cost at a rate equal to applicable bank rate plus 3 per cent. MPWD shall also reimburse O&M expenses adjusted to Price Index Multiple on the annuity payment dates to BNCPIPL. Strong operational and financial support from the sponsor BNC Power Projects Limited (BNCPPL) has decades of experience in the civil construction, electrical-transmission and substations segments. The sponsor holds 59.68% shares of the company and provides funds and technical support to the project. The company has achieved revenues of Rs. 102.89 Cr. till August 2024. BNCPPL has a healthy order book of about ~Rs.1433 Cr. (unexecuted) till 31st August 2024 from electrical transmissions, substations and road divisions. The OB/OI stood at 4.33 times till 31st August 2024. The sponsor has provided corporate guarantees on the bank loans of the Company. Acuite believes that the sponsor is expected to provide technical or funding support in case of any exigency over the medium term. Waterfall Mechanism in Escrow Mechanism The loan is repayable under defined waterfall mechanism. The repayments for term loan will be recovered from Escrow account. BNCPIPL has an escrow mechanism through which all transactions related to the project will be routed. Any surplus in the escrow account will be kept reserved for future Major Maintenance subject to minimum of one instalment and total project MMR expenses due at any given point of time. Only surplus cash flow after meeting operating expense, debt servicing obligation, and provision for major maintenance expense, can be utilised as per borrower’s discretion during the concession period. The debt service coverage ratio (DSCR) is expected to remain at over 1.43 times for the tenure of the loan. |
Weaknesses |
Susceptibility to risks related to delay in receipt of annuity and changes in operational cost & interest rate
As per the concession agreement, the company is expected to receive a semi-annual annuity. Any delay in timely receipt of the annuity could adversely impact debt-servicing ability. Along with fixed annuities, the project will receive interest payments on the balance annuities that are linked to the prevailing bank rate. The bank rate has reduced significantly in past couple of years which has impacted the project inflow as a large proportion of the cash inflow is from the interest on balance annuities. However, this risk is partially offset as the interest rate on debt is floating and is also expected to follow the trend in bank rates thus keeping DSCR in check. Further, the company is exposed to risks related to maintenance of the project. If the prescribed standards are not met, annuity payment may be reduced. Any significant delay and deduction in annuities could impact the debt servicing ability of the company. However, strong track record of sponsor, who is also the O&M contractor, is expected to mitigate this risk. |
Rating Sensitivities |
|
Liquidity Position |
Adequate |
BNCPIPL’s liquidity position is adequate marked by continuous support from the parent BNC Power Projects limited (BNCPPL). The project was completed, and the company has started receiving the annuity from Maharashtra PWD since November 2022. The DSCR is expected to be adequate, and the company maintains cash and cash equivalents and payments received by MPWD will cushion liquidity. Fund support is likely from sponsor for any exigency including O&M and major maintenance expenses. Acuite believes that the liquidity of BNCPIPL is likely to remain adequate backed by consistent support from sponsor and government in terms of annuity payments.
|
Outlook: Stable |
|
Other Factors affecting Rating |
None |
Particulars | Unit | FY 24 (Actual) | FY 23 (Actual) |
Operating Income | Rs. Cr. | 3.54 | 13.34 |
PAT | Rs. Cr. | (1.73) | 6.45 |
PAT Margin | (%) | (48.85) | 48.36 |
Total Debt/Tangible Net Worth | Times | 6.70 | 4.94 |
PBDIT/Interest | Times | 0.47 | 2.42 |
Status of non-cooperation with previous CRA (if applicable) |
None |
Any other information |
None |
Applicable Criteria |
• Default Recognition :- https://www.acuite.in/view-rating-criteria-52.htm • Service Sector: https://www.acuite.in/view-rating-criteria-50.htm • Infrastructure Sector: https://www.acuite.in/view-rating-criteria-51.htm • Application Of Financial Ratios And Adjustments: https://www.acuite.in/view-rating-criteria-53.htm • Group And Parent Support: https://www.acuite.in/view-rating-criteria-47.htm |
Note on complexity levels of the rated instrument |
Rating History : |
Not Applicable |
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|